New drainage analysis found the 45th Street East storm system between Avenue R and Avenue R-8 can't handle current runoff, so the city is expanding the design contract to add four new catch basins. Flooding on that stretch has been a known problem.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 7, 2026.
Impact analysis
$54,625 more for the Psomas design contract plus up to $877,189 for construction management — paid from Drainage Funds.
Drivers and residents along 45th Street East who deal with flooding and deteriorating pavement.